M
monstadunk
I am working on a company project that has many links, both inside of its
self and to Excel. When I try to pdate the links I get the following error:
"The operation cannot complete because the source file contains invalid
project data or the total number of rows would excede the limit of 1,0480,000
rows in a project."
I know that the error has to be comming from some sort of invalid project
data because I actaully only have 3500 rows.
I have taken the project over from someone else. That person made a lot of
wierd categories because he didn't know what all the other categories do. The
ones that I think are causing a problem are the custom number categories
called Estimated Quantity (same thing as work) and Quantity Completed (same
as actual work). Then he tied those two in to another custom number category
ambiguously named Number 3 and linked Number 3 to % Complete. The only reason
I can see for him to do this would be to get rid of the "hrs." label in the
Work category. The work is being tracked in Welding Inches, not hours.
Is there anyway I can remove the "hrs." label from the Work categories? That
might fix my problem, as well as reduce the number of links on this project.
As it is, it takes a few minutes to load on some of the slower machines,
longer if the server traffic is high.
Thanks.
self and to Excel. When I try to pdate the links I get the following error:
"The operation cannot complete because the source file contains invalid
project data or the total number of rows would excede the limit of 1,0480,000
rows in a project."
I know that the error has to be comming from some sort of invalid project
data because I actaully only have 3500 rows.
I have taken the project over from someone else. That person made a lot of
wierd categories because he didn't know what all the other categories do. The
ones that I think are causing a problem are the custom number categories
called Estimated Quantity (same thing as work) and Quantity Completed (same
as actual work). Then he tied those two in to another custom number category
ambiguously named Number 3 and linked Number 3 to % Complete. The only reason
I can see for him to do this would be to get rid of the "hrs." label in the
Work category. The work is being tracked in Welding Inches, not hours.
Is there anyway I can remove the "hrs." label from the Work categories? That
might fix my problem, as well as reduce the number of links on this project.
As it is, it takes a few minutes to load on some of the slower machines,
longer if the server traffic is high.
Thanks.