Strange Functionality

G

Guest

I have several very complex project plans that I've been
working with for several months.

Recently, when I open the plans, some of the dates
randomly jump forward in time, despite the fact I havent
made any changes...

So to recap, I open a plan and some of the tasks shift
way out into the future for no apparent reason...

TIA
 
D

Dale Howard [MVP]

anonymous --

There could be a couple of explanations for this:

1. Someone leveled your project against one or more other projects in the
portfolio
2. Your resource pool administrator added nonworking time to the calendars
of one or more resources

Without looking at your project, I cannot be sure of the cause. Hope these
ideas help.
 