Two questions about this strange Portfolio Modeler (Project Server 2003
SP2):
1° - When the pointer hovers a project summary bar, a tooltip popups and
announce:
- Start: 31st December 2049
- Finish: 26th march 1984
It's not very helpful! Is it a bug or did I put too much whiskey in my
coffee?
2° - The red bars reveal an over allocation. But is it *in* the selected
project or does it comes from a conflict between 2 projects? When I examine
resource by resource, there is no over allocation at all ! And there is no
couple of parallel red bars.
Thanks for help,
Newbie
Two questions about this strange Portfolio Modeler (Project Server 2003
SP2):
1° - When the pointer hovers a project summary bar, a tooltip popups and
announce:
- Start: 31st December 2049
- Finish: 26th march 1984
It's not very helpful! Is it a bug or did I put too much whiskey in my
coffee?
2° - The red bars reveal an over allocation. But is it *in* the selected
project or does it comes from a conflict between 2 projects? When I examine
resource by resource, there is no over allocation at all ! And there is no
couple of parallel red bars.
Thanks for help,
Newbie