Strange time split

J

Jeff

Can anybody help me find the cause of this annoying problem?

The enterprise calendar has a date marked as non-working (it's a holiday),
yet many resources actually end up working on that day. They report their 8
hours via PWA. The manager accepts their entries and updates the project
plan. The Resource time sheet in PWA, the Project Plan and the Resource
Assignments view in PWA all show the resources' 8 hours on that day. YET the
OLAP cube shows their hours divided between two days (3 hrs on the day
before and 5 on the actual day) What is up with that???
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top