M
Martin Wilkinson
Extending a fixed work task's duration only re-spreads work for resources
whose work already "runs up" against the end date. Other resource's work
distribution remains unchanged.
I have a task which is Fixed Work.
The task has two resources called R1 and R2
R1 has 7 hours work, R2 has 10 hours work. The task has 17 hours total Work.
Both resources have a working time of 7 hours per day.
The task starts on Monday, so in Task Usage view, R1 is shown as working all
his 7 hours on Monday. R2 works 7 hours on Monday and the remaining 3 hours
on Tuesday.
If I extend the Duration to 3 days, R2’s work is recalculated to spread it
more thinly out over the new, longer duration. This is expected. However,
R1’s work remains all on the Monday – it is not spread out over the longer
duration.
If I use the Gantt view to shorten the end date of the task so that all the
work takes place in one day, then re-extend the end date, both resource’s
work is recalculated to spread it more thinly out over the new, longer
duration.
It looks as though only those Resources whose work “runs up to†the task’s
end date have their Work re-scheduled when the task is stretched.
Trivial example, but shows the principle of something which has caught me
out. I had a task with several resources which I wanted to spread out, as the
resources were overloaded. I “stretched†the task to try to spread the entire
work for the task over the extended duration, but Project only spread one of
the resource’s work over the extended duration (the one whose work “hit†the
task’s end date). The other resource’s work stayed at the front end of the
task, which meant I still had a peak at the front of the task.
Has anyone experienced this behaviour or have any comment?
whose work already "runs up" against the end date. Other resource's work
distribution remains unchanged.
I have a task which is Fixed Work.
The task has two resources called R1 and R2
R1 has 7 hours work, R2 has 10 hours work. The task has 17 hours total Work.
Both resources have a working time of 7 hours per day.
The task starts on Monday, so in Task Usage view, R1 is shown as working all
his 7 hours on Monday. R2 works 7 hours on Monday and the remaining 3 hours
on Tuesday.
If I extend the Duration to 3 days, R2’s work is recalculated to spread it
more thinly out over the new, longer duration. This is expected. However,
R1’s work remains all on the Monday – it is not spread out over the longer
duration.
If I use the Gantt view to shorten the end date of the task so that all the
work takes place in one day, then re-extend the end date, both resource’s
work is recalculated to spread it more thinly out over the new, longer
duration.
It looks as though only those Resources whose work “runs up to†the task’s
end date have their Work re-scheduled when the task is stretched.
Trivial example, but shows the principle of something which has caught me
out. I had a task with several resources which I wanted to spread out, as the
resources were overloaded. I “stretched†the task to try to spread the entire
work for the task over the extended duration, but Project only spread one of
the resource’s work over the extended duration (the one whose work “hit†the
task’s end date). The other resource’s work stayed at the front end of the
task, which meant I still had a peak at the front of the task.
Has anyone experienced this behaviour or have any comment?