Sub-Project - Project Summary Tasks showing on a Master Project

S

Steve Scott

hi, I have custom information set at project summary level ie task 0 in
individual projects. When I roll these up into a Master Plan I can't seem to
get the individual task 0s for all the plans to show is this possible?
 
S

Steve Scott

Hi, I have done that and it still isnt doing what I need..all I get in the
Master project is the insertion line and the the task 1s of each sub-project
below them?
 
J

JulieS

Hi Steve,

When you create a master project, the line showing the inserted
project plan is automatically generated by Project. If for example,
you display the project summary task line (Line 0) in Project A and
added text into the Text1 field and then added Project A into a
master project. The value you typed into the Text1 field would not
show on the inserted project summary line in the master project.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.