- Joined
- Oct 6, 2017
- Messages
- 1
- Reaction score
- 0
hi,
I am trying to work with sub projects, I have 4 subprojects in a master project file, I need to calculate the delay and the the overall % Complete Planned, I see that it is calculating already the overall % Completed, is it possible to do?
Thanks
Gustavo
I am trying to work with sub projects, I have 4 subprojects in a master project file, I need to calculate the delay and the the overall % Complete Planned, I see that it is calculating already the overall % Completed, is it possible to do?
Thanks
Gustavo