W
wdritt
Hello, I have a master project with 13 or so sub projects inserted in it. I
have this setup in Proj Pro to show "Inserted projects are calculated like
summary tasks"
I also have the master project itself displaying the project summary task.
My problem is that the master project's summary task appears to be combining
the sub project info in regards to the Duration. This in turn is pushing out
my Finish date.
So in this case my projects range in the 400-700 day range, all starting in
January of 2008. The master project summary row shows a duration of 9000
days and a finish date of 2042. When it should be showing the duration as
744 and the end date in 2010.
I assume I am missing a setting somewhere. I have recreated this and
reviewed all of my settings, but still get this problem.
have this setup in Proj Pro to show "Inserted projects are calculated like
summary tasks"
I also have the master project itself displaying the project summary task.
My problem is that the master project's summary task appears to be combining
the sub project info in regards to the Duration. This in turn is pushing out
my Finish date.
So in this case my projects range in the 400-700 day range, all starting in
January of 2008. The master project summary row shows a duration of 9000
days and a finish date of 2042. When it should be showing the duration as
744 and the end date in 2010.
I assume I am missing a setting somewhere. I have recreated this and
reviewed all of my settings, but still get this problem.