Sub-sub tasks under sub-tasks

B

binojkr

I am a novice to MS Project.



I have a project management requirement as follows:


I want to monitor and manage some seven sub-sub tasks under some 20 su
tasks. To make it more clear, I want to monitor the Drawing sheet statu
of plan, elevation, section etc(7 of them in general, but if there ar
multiple sheets for sections, then the number goes up). These are m
sub-sub tasks. These appear under some 20 odd areas like single room
double room, lobby etc.. which I assume are sub tasks.

In excel i could use multiple sheets and a row colum matrix of 20x7 t
manage this problem. In MS Project, I did not come across any suc
facility of row column matrix or linking multiple sheets kind of stuff
Since MS Project deals with each sub (sub-sub) task as a row, I presum
that I must have 20x7 = 140 odd rows, with the same kind of names (pla
elevation...) repeated, making it combursome and difficult t
understand.
Moreover, I may have to include yet another sub level under a few o
these sub-sub levels.

How do I solve this problem?

Pls help.



Thanks a lot in advance.

Binoj. (e-mail address removed)
 
B

B Sai Prasad [PMP]

Dear Binojkr -

I understand you have the executable tasks in each sheet of workbook.

The fundamental idea is to consider each sheet "name" of the workbook as
summary task / phase in the schedule and have the rows in each workbook as
individual (executable) tasks in the schedule.

As you a beginner to Microsoft Project, I would like to suggest the
following approach to migrate the data from workbook to Microsoft Project.

1. Open MS Project and choose File, Open to use the Import Wizard to map the
columns in sheet to fields in MS Project.
2. Repeat step 1 for each sheet in the workbook
3. Now, it would be cumbersome for you to understand the schedule due to the
size and all the tasks are in the same level. So, you can insert rows between
the different phases - like plan, elevation, section
4. Select (only) the "executable" tasks under the phase and choose Indent
(->) arrow in Formatting tool. This will push these tasks and outline the
schedule.

If my suggestion is useful, consider rating it :)
 
S

Steve House [MVP]

Project is certainly able to handle that level of complexity, piece of cake.
The outline structure can theoretically accomodate up to 65000 levels of
indentation. But you are correct that you will have many of your
performance tasks repeated. The task list is essentially decomposed by
deliverable so you'll end up with

Paint Interior
Paint Living Room
Prep Walls
Paint Walls
Mix Paint
Apply Paint
Cleanup drips
Paint Master Bedroom
Prep Walls
Paint Walls
Mix Paint
Apply Paint
Cleanup drips
etc
etc
etc
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top