D
Diggers
hello,
I have the following problem. I am trying to create a project plan that will
show the following.
I have a Main Task that should last 4 months. So starts September 1st and
finished December 31st. This task has 3 sub tasks which will take place
during those 4 months, however the length my work in the subtasks is as
follows:
Task1 lasts 20 days
Task2 lasts 10 days
Task3 lasts 10 days.
For the life of me I cannot get the main task to show 4 months and then the
subtasks to show 20,10 and 10? Has anyone any idea how this can be displayed
in MS Project?
Thanks
I have the following problem. I am trying to create a project plan that will
show the following.
I have a Main Task that should last 4 months. So starts September 1st and
finished December 31st. This task has 3 sub tasks which will take place
during those 4 months, however the length my work in the subtasks is as
follows:
Task1 lasts 20 days
Task2 lasts 10 days
Task3 lasts 10 days.
For the life of me I cannot get the main task to show 4 months and then the
subtasks to show 20,10 and 10? Has anyone any idea how this can be displayed
in MS Project?
Thanks