Subcontractor cost as a lump sum?

S

SeanG

In Project, if I have a subcontractor cost that is broken into various lump
suims how do I fit that into Project's resource sheets?
 
M

Mike Glen

Hi Sean,

Welcome to this Microsoft Project newsgroup :)

I would produce a milestone for each payment day and assign a fixed cost for
the amount.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 