G
GHMontgomery
First off, thanks in advance for any help or guidance anyone can provide me
on this issue - it appeared yesterday and I have thus far been unable to
trace the root of the problem.
Server: Project Server 2007
Scenario: Team Member accessed PWA->My Tasks and performed the following
actions:
1. Clicked on the Progress cell for a specific task ("Task A") and entered
Actual Work values for three days.
2. Clicked on the Progress cell for another task ("Task B") and entered
Actual Work values for three days.
3. Marked the checkbox next to Task A and Task B.
4. Clicked on the Submit Selected button.
The Status Manager (also the PM/owner of the project) received the e-mail
alert that task assignment updates had been submitted.
Issue: The submitted task assignment updates are not showing up under the
Task Updates page for the Status Manager. The submitted task assignment
updates also do not trigger a "Review Submitted Updates" popup when the
project is opened from within Project Professional 2007.
The Status Manager reports that this has happened before, for a different
user on a different project, and that the previous action taken was to
manually enter the Actuals into the project using Project Professional 2007.
The Status Manager has agreed to hold off taking further action for a few
days so I can troubleshoot the server to pinpoint any possible cause of the
missing data.
The Enterprise Resource profile of the submitting Team Member has been
checked and double-checked to verify information accuracy. The submitting
Team Member has successfully submitted updates to this project using the same
process up until now.
===========
Gina Montgomery
on this issue - it appeared yesterday and I have thus far been unable to
trace the root of the problem.
Server: Project Server 2007
Scenario: Team Member accessed PWA->My Tasks and performed the following
actions:
1. Clicked on the Progress cell for a specific task ("Task A") and entered
Actual Work values for three days.
2. Clicked on the Progress cell for another task ("Task B") and entered
Actual Work values for three days.
3. Marked the checkbox next to Task A and Task B.
4. Clicked on the Submit Selected button.
The Status Manager (also the PM/owner of the project) received the e-mail
alert that task assignment updates had been submitted.
Issue: The submitted task assignment updates are not showing up under the
Task Updates page for the Status Manager. The submitted task assignment
updates also do not trigger a "Review Submitted Updates" popup when the
project is opened from within Project Professional 2007.
The Status Manager reports that this has happened before, for a different
user on a different project, and that the previous action taken was to
manually enter the Actuals into the project using Project Professional 2007.
The Status Manager has agreed to hold off taking further action for a few
days so I can troubleshoot the server to pinpoint any possible cause of the
missing data.
The Enterprise Resource profile of the submitting Team Member has been
checked and double-checked to verify information accuracy. The submitting
Team Member has successfully submitted updates to this project using the same
process up until now.
===========
Gina Montgomery