Hello everyone!
I've created a macro which calculates several custom fields for every task
in a project, including the SUMMARY TASK. The thing is: when I create a
Master Project, the summary row for each sub-project doesn´t show the values
that it should for this fields. Always shows 0%, but if open the individual
sub-project, the summary task does show the right values.
Why is this happening? What do I have to do to display the values for each
sub-project's summary task in the master? How do I roll up this values to the
Master's summary task?
Thanks for your help!
I've created a macro which calculates several custom fields for every task
in a project, including the SUMMARY TASK. The thing is: when I create a
Master Project, the summary row for each sub-project doesn´t show the values
that it should for this fields. Always shows 0%, but if open the individual
sub-project, the summary task does show the right values.
Why is this happening? What do I have to do to display the values for each
sub-project's summary task in the master? How do I roll up this values to the
Master's summary task?
Thanks for your help!