Subproject summary fields in master project

S

Sebastian Cordoba

Hello everyone!

I've created a macro which calculates several custom fields for every task
in a project, including the SUMMARY TASK. The thing is: when I create a
Master Project, the summary row for each sub-project doesn´t show the values
that it should for this fields. Always shows 0%, but if open the individual
sub-project, the summary task does show the right values.

Why is this happening? What do I have to do to display the values for each
sub-project's summary task in the master? How do I roll up this values to the
Master's summary task?

Thanks for your help!
 
R

Rod Gill

Hi,

Project does not rollup custom fields in consolidations, or Baseline data.
This has been so for many versions. I seem to be giving this response more
and more, so please propose a feature update (full rollup of timephased and
custom data in consolidations) to your local Microsoft office. If enough of
us do this, maybe we'll get it!

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 