K
kanguyen
In my project, I've setup a bunch of milestone dates (duration: 0 days)
for example - the announce date for a product, which is April 30, 2010.
I have some tasks in my project plan which require things to be done b
exactly 1 month (or 30 days) prior to the announce date. I've also se
these up as zero-duration milestones.
However, when I set up my predecessor lag times as FS or FF minus
month or 30 days, I get March 19, 2010.
Does this have to do with working time? I really just need it t
backtrack roughly a month plus or minus a day - so March 30 or 31.
Any ideas
for example - the announce date for a product, which is April 30, 2010.
I have some tasks in my project plan which require things to be done b
exactly 1 month (or 30 days) prior to the announce date. I've also se
these up as zero-duration milestones.
However, when I set up my predecessor lag times as FS or FF minus
month or 30 days, I get March 19, 2010.
Does this have to do with working time? I really just need it t
backtrack roughly a month plus or minus a day - so March 30 or 31.
Any ideas