D
Dan_W
I have used Microsoft Project to create a detailed list of tasks, assigned
resources to all tasks and entered work days per resource per task. The
resources working on this project have variable and unpredictable schedules
that make it impossible to schedule their work on specific calendar days.
Instead, I want to schedule work in terms of requested task-work-days per
quarter (ideally bi-monthly but this does not appear to be an available unit)
then evaluate whether we have sufficient resources to accomplish the work
(e.g., Resource A has 60 days/quarter available but is being asked to
contribute to 10 tasks totaling 80 days in Qtr 1). I'm only interested in
person-work-days per quarter (that's "Work" days and NOT "Duration" days) and
specific start & end dates within a quarter are meaningless. My needs are
pretty simple but I cannot figure out an approach in Project to plan by
quarter and determine if we are over or under resourced by quarter.
resources to all tasks and entered work days per resource per task. The
resources working on this project have variable and unpredictable schedules
that make it impossible to schedule their work on specific calendar days.
Instead, I want to schedule work in terms of requested task-work-days per
quarter (ideally bi-monthly but this does not appear to be an available unit)
then evaluate whether we have sufficient resources to accomplish the work
(e.g., Resource A has 60 days/quarter available but is being asked to
contribute to 10 tasks totaling 80 days in Qtr 1). I'm only interested in
person-work-days per quarter (that's "Work" days and NOT "Duration" days) and
specific start & end dates within a quarter are meaningless. My needs are
pretty simple but I cannot figure out an approach in Project to plan by
quarter and determine if we are over or under resourced by quarter.