J
johnny nui
I am having problems with successor changing the dates of a predecessor.
here is my scenario
task A has a Deadline of 10/15 and is of type "As Late as Possible" and
indeed finishes on 10/15 as it should.
task B cannot be completed before task A
when i created task B the start date was 9/30
when i make task B a successor to task A and set it to "As soon as possible"
what happens is that task A is moved so that it finishes before 9/30
I want task B to start after 10/15 or whatever the finish date is on task A,
how do i accomplish this?
I have another situation in the same project that seems to work fine, but i
cannot see what is different
here is my scenario
task A has a Deadline of 10/15 and is of type "As Late as Possible" and
indeed finishes on 10/15 as it should.
task B cannot be completed before task A
when i created task B the start date was 9/30
when i make task B a successor to task A and set it to "As soon as possible"
what happens is that task A is moved so that it finishes before 9/30
I want task B to start after 10/15 or whatever the finish date is on task A,
how do i accomplish this?
I have another situation in the same project that seems to work fine, but i
cannot see what is different