Hi
My file was working fine until I moved some tasks around. To move the tasks
I clicked on the task number and dragged and dropped the task them to another
location higher up the task list.
Now when I change the end date of a task the successor does not move.
I followed the suggestions from the online help for "I linked my tasks, but
now the successor task doesn't move" with no results.
Any ideas what is going on?
Did I not properly move the tasks when I clicked and dragged? Was I
suppossed to cut and paste? I opend a new file and created a few tasks and
tried to cut and paste and still the same problem.
Help
Thanks
My file was working fine until I moved some tasks around. To move the tasks
I clicked on the task number and dragged and dropped the task them to another
location higher up the task list.
Now when I change the end date of a task the successor does not move.
I followed the suggestions from the online help for "I linked my tasks, but
now the successor task doesn't move" with no results.
Any ideas what is going on?
Did I not properly move the tasks when I clicked and dragged? Was I
suppossed to cut and paste? I opend a new file and created a few tasks and
tried to cut and paste and still the same problem.
Help