A
Amy Ritter
I have two tasks, A and B. Task B is set as the
successfor for task A with FS start relationship. Task A
was set to end on 9/29, however Task B has a start date
of 9/18 and I have to manually change the start date for
Task B if I want it to line up correctly for the FS
relationship with Task A (start date should be 9/30). I
am concerned that if dates change, the successor start
date won't update automatically. Can anyone tell me why
this is happening?
successfor for task A with FS start relationship. Task A
was set to end on 9/29, however Task B has a start date
of 9/18 and I have to manually change the start date for
Task B if I want it to line up correctly for the FS
relationship with Task A (start date should be 9/30). I
am concerned that if dates change, the successor start
date won't update automatically. Can anyone tell me why
this is happening?