Successors / Predecessors

S

smudge20

I have to use two projects for the activities that are ongoing. Is there a
way to link successors / predecessors in the two projects. Basically it is a
pipeline job and I have civils work to be done prior to mechanical/pipework.
The mechanical part obviously cannot start until the civils work has been
done. I'd like to link them if possible to FS / SS. Thanks
 
J

Jan De Messemaeker

Hi,

Open a new file
Through Insert, Project, insert both projects
"Open" them by clicking the + sign
link the tasks as if they belonged to the same project
Close and save;
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top