I have to use two projects for the activities that are ongoing. Is there a
way to link successors / predecessors in the two projects. Basically it is a
pipeline job and I have civils work to be done prior to mechanical/pipework.
The mechanical part obviously cannot start until the civils work has been
done. I'd like to link them if possible to FS / SS. Thanks