I am so frustrated here any help would be greatly appreciated. I am trying to
link tasks in a simple finish to start relationship but the tasks linked do
not move outward on the calendar. They all still start at the same time. I
already moved the calculation to automatic. I have spent a whole day on this.
any help?
 
J

Jack Dahlgren

Is there an actual start date for the successor task?
That would pin it in place. Also look for any constraint other than "as soon
as possible"

-Jack
 