H
Hisham
Hello Microsoft:
This is a suggestion to Microsoft for introducing a new column, which I
would like to call: the (Planned % Complete) in Microsoft Project. This field
will be similar to the seeded column (% Complete) however, the new suggested
column should get calculated automatically to reflect what should it be the
(% Complete) assuming that the project is performing just on-time. We have
actually developed this enhancement through customizing the custom fields
available in Microsoft Project and it was very useful to have it along with
the seeded (% Complete) for schedule and potential delay analysis.
The new suggested column (Planned % Complete) shall perform in away similar
to the seeded function: "Update work as complete through" which is available
in MS Project "Tools -> Tracking -> Update Project" however, the difference
here that the seeded function "update project" overwrites the (% Complete)
causing loss of the actual values in (% Complete) which is usually captured
manually at best judgment of project team feedback of the project progress.
I have published a post regarding this matter, so please visit my blog to
read more about the suggested enhancement of the (Planned % Complete) at the
following url: http://epmforum.wordpress.com/2008/05/28/planned-pct-complete/
Regards,
Hisham Aqtash
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...88e0-cfe76f14505c&dg=microsoft.public.project
This is a suggestion to Microsoft for introducing a new column, which I
would like to call: the (Planned % Complete) in Microsoft Project. This field
will be similar to the seeded column (% Complete) however, the new suggested
column should get calculated automatically to reflect what should it be the
(% Complete) assuming that the project is performing just on-time. We have
actually developed this enhancement through customizing the custom fields
available in Microsoft Project and it was very useful to have it along with
the seeded (% Complete) for schedule and potential delay analysis.
The new suggested column (Planned % Complete) shall perform in away similar
to the seeded function: "Update work as complete through" which is available
in MS Project "Tools -> Tracking -> Update Project" however, the difference
here that the seeded function "update project" overwrites the (% Complete)
causing loss of the actual values in (% Complete) which is usually captured
manually at best judgment of project team feedback of the project progress.
I have published a post regarding this matter, so please visit my blog to
read more about the suggested enhancement of the (Planned % Complete) at the
following url: http://epmforum.wordpress.com/2008/05/28/planned-pct-complete/
Regards,
Hisham Aqtash
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...88e0-cfe76f14505c&dg=microsoft.public.project