R
Rene Bongers
Hello,
We have a problem with our Microsoft Project Server 2007 (SP2)
In the resource usage view I see the resource and below the tasks of
this project and the other projects the resource works for.
On the right side (time phased data) I see above all the tasks and projects
the sum of the actual work. The sum is the complete sum of all actual from
the resource. Only this sum is not right. We I open all the projects on which
the resource also should work, the sum is corrected and right.
We thought that this would be solved by the last hotfix and SP2.
Any body a idea how we can solve this problem?
Thanks in advance
We have a problem with our Microsoft Project Server 2007 (SP2)
In the resource usage view I see the resource and below the tasks of
this project and the other projects the resource works for.
On the right side (time phased data) I see above all the tasks and projects
the sum of the actual work. The sum is the complete sum of all actual from
the resource. Only this sum is not right. We I open all the projects on which
the resource also should work, the sum is corrected and right.
We thought that this would be solved by the last hotfix and SP2.
Any body a idea how we can solve this problem?
Thanks in advance