Sum of actual work not correct in ressource assignment view

H

Hans Wurst

Project Server:

Hi there,

in ressource assignment view I see the ressource and below it the tasks of
this project and the other projects the ressource works for.

On the right side (timephased data) I see above all the tasks and projects
the sum of the actual work. The sum is the complete sum of all actuals (all
projets) the ressource entered - but I wanna the the sum of the actuals of
the acutal project, not the sum of all projects.

god - did you understand my problem?

My first idea was to group the projects or use the filter "projetteam" - but
it all doesn't help :-(

Any idea?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top