H
Hans Wurst
Project Server:
Hi there,
in ressource assignment view I see the ressource and below it the tasks of
this project and the other projects the ressource works for.
On the right side (timephased data) I see above all the tasks and projects
the sum of the actual work. The sum is the complete sum of all actuals (all
projets) the ressource entered - but I wanna the the sum of the actuals of
the acutal project, not the sum of all projects.
god - did you understand my problem?
My first idea was to group the projects or use the filter "projetteam" - but
it all doesn't help :-(
Any idea?
Hi there,
in ressource assignment view I see the ressource and below it the tasks of
this project and the other projects the ressource works for.
On the right side (timephased data) I see above all the tasks and projects
the sum of the actual work. The sum is the complete sum of all actuals (all
projets) the ressource entered - but I wanna the the sum of the actuals of
the acutal project, not the sum of all projects.
god - did you understand my problem?
My first idea was to group the projects or use the filter "projetteam" - but
it all doesn't help :-(
Any idea?