Summarizing milestones in Project 2003

B

Barry Gray

I'd like to create a section at the top of my schedule that summarizes all of
the milestone tasks in the body of the schedule below. As I mark milestones
complete, or reschedule them as necessary, I'd like the changes to
automatically reflect in the milestone summary at the top.

Is this possible?
 
G

Gérard Ducouret

Hello Barry,

Yes, this is possible. Use the Tracking Gantt where the Rolled up Baseline
Milestone and the Rolled up Milestone symbols are already created.(Look in
the Format / Bar Styles dialog)
In the Task information of a milestone, General tab, click the roll up gantt
bar to summary option.

Hope this helps,

Gérard Ducouret
 