A
Andrew
I have a formula which works out the planned % for individual bars - works
great. The problem I have is with the summary bars. My formula works in a
straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
method to calculate the actual % of summary bars - I understand how it does
it, what I was hoping for is there somebody out there that could issue a
formula (via a macro) that copies that method, as at the moment the two do
not correlate.
Thanks in anticipation.
Andrew
great. The problem I have is with the summary bars. My formula works in a
straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
method to calculate the actual % of summary bars - I understand how it does
it, what I was hoping for is there somebody out there that could issue a
formula (via a macro) that copies that method, as at the moment the two do
not correlate.
Thanks in anticipation.
Andrew