I have a "Fixed Work" project that has fixed number of hours for each task. I
have been updating the Physical % Complete. I have the following questions:
1) When i update the physical % complete (or % complete in the gantt chart),
it does not update the % complete for the task???
2) Even if i enter the % complete for the tasks, it does not update the
summary % complete for the task rollup or for the project?
What should i do differently to see the overall % complete as well as
individual summary tasks complete?
Thanks
JAck