J
JWeaver
I have the following section on my project schedule. I think the duration on
the summary task, general testing, should show 7.5 hours. It shows 0. There
are several other sections doing the same thing. Yet there are sections that
are working correctly. I can't figure out the pattern. All 4 tasks have the
same resource assigned to it. The tasks are not linked. See details below.
General testing 0 hours 09/23/07 8:00 a.m. 09/23/07 5:00 p.m.
Test setup validations 2 hrs 09/23/07 8:00 AM 09/23/07 10:00 AM
Rebuild user report table 4 hrs 09/23/07 8:00 AM 09/23/07 12:00 PM
Perform database reorg of GEN 3.5 hrs 09/23/07 1:30 PM 09/23/07 5:00 PM
Perform database reorg of HRTEST 3.5 hrs 09/23/07 1:30 PM 09/23/07 5:00
PM
the summary task, general testing, should show 7.5 hours. It shows 0. There
are several other sections doing the same thing. Yet there are sections that
are working correctly. I can't figure out the pattern. All 4 tasks have the
same resource assigned to it. The tasks are not linked. See details below.
General testing 0 hours 09/23/07 8:00 a.m. 09/23/07 5:00 p.m.
Test setup validations 2 hrs 09/23/07 8:00 AM 09/23/07 10:00 AM
Rebuild user report table 4 hrs 09/23/07 8:00 AM 09/23/07 12:00 PM
Perform database reorg of GEN 3.5 hrs 09/23/07 1:30 PM 09/23/07 5:00 PM
Perform database reorg of HRTEST 3.5 hrs 09/23/07 1:30 PM 09/23/07 5:00
PM