H
Hadi
Hello Experts,
I have been using MS Project 2003 for several years now, but recently
started to use PWA for reporting, etc. I noticed a problem with the duration
on the summary tasks inside PWA. For example, I setup a Project Center view
to group by one of my Enterprise Project Text Fields. The Duration at that
summary level is adding up all of the durations for the projects below. what
is the issue? I am not the admin and not sure if our admin is keeping up with
all of the SPs and hot fixes.
Thank you,
I have been using MS Project 2003 for several years now, but recently
started to use PWA for reporting, etc. I noticed a problem with the duration
on the summary tasks inside PWA. For example, I setup a Project Center view
to group by one of my Enterprise Project Text Fields. The Duration at that
summary level is adding up all of the durations for the projects below. what
is the issue? I am not the admin and not sure if our admin is keeping up with
all of the SPs and hot fixes.
Thank you,