A
Aschwin Beurskens
I've just switched to project 2003 professional. My
project plans have almost doubled in work effort (and thus
in costs). It looks like the summary for 'work' adds the
summary duration. An example:
task work duration resource
3. Design 11 4
3.1 task 1 4 4 resource1
3.2 task 2 2 2 resource1
3.3 task 3 1 1 resource2
No matter what I try (starting from scratch, changing
effort driven on/off, a mix a resources) I end up with
similar results.
Is this a bug (feature;-) or am I doing something
basically wrong?
project plans have almost doubled in work effort (and thus
in costs). It looks like the summary for 'work' adds the
summary duration. An example:
task work duration resource
3. Design 11 4
3.1 task 1 4 4 resource1
3.2 task 2 2 2 resource1
3.3 task 3 1 1 resource2
No matter what I try (starting from scratch, changing
effort driven on/off, a mix a resources) I end up with
similar results.
Is this a bug (feature;-) or am I doing something
basically wrong?