Hello Deluth,
You may wish to look at the resource sheet with the work
table applied.
It will show:
Resource Name, % Work complete, Scheduled Work, OT Work,
Baseline Work, Work Variance, Actual Work,Remaining Work
The default format is to see Work in hours. If you want
to see the information in days:
Tools --> Options --> Schedule tab
Change "Work is entered in" to Days.
Hope this helps.
Julie
-----Original Message-----
Is there a way for me to "roll up" a summary of each
resources? I would like to get a summary of their
progress - how many days they originally have to work,
how many days have they completed and how much longer
before they finish. Much appreciated any help.