Hi CQ,
there are several dates you can have on a project field. The Start date and
the finish date of actual, forecast and baseline.
I assume that your summary progress field is a calcuated field that looks at
the Status Date of your project. The status date is not an out of the box
project center date that you can simply include. You will need to create a
Project custom field and enter a formula that simply says [status date]. This
custom field can then be used to include into your project center view and it
will show you the status date of the project.
I hope that is what you are after
--
Marc Soester [MVP]
http://marcsoester.blogspot.com
:
Let me clarify - the Summary Progress Date for the entire schedule, not a
specific task.
:
In Project Server 2003, we were using the field for the "Summary Progress
Date" for our reports. I can't seem to find that field in Project Server
2007. Can somebody help me out if it still exists?