J
JenStover
I am on MSPS 2003.
When I click the 'Load Summary Resource Assignments' option at start up, I
am seeing 'Remaining Work' in projects in which there is no remaining work.
I have re-published, over-typed the existing zero and re-published, and a
couple of other things.
What could be causing this?
Thanks!
When I click the 'Load Summary Resource Assignments' option at start up, I
am seeing 'Remaining Work' in projects in which there is no remaining work.
I have re-published, over-typed the existing zero and re-published, and a
couple of other things.
What could be causing this?
Thanks!