Summary Resource Assignments' Task data in Resource Usage View

C

Conrad Santiago

We are using Project Server 2003.
With one project checked out, in the Resource Usage view, under each
resource, I can see the project names in which the resource has other
assignments, however, I cannot see the task name or names within the listed
projects.

Is there a way to see the assignment task name, or other task data, of the
projects shown in this view? That is, of course, short of checking out the
project and hunting down the assignments.

Thanks in advance for any responses.
Conrad Santiago
 
D

Dale Howard [MVP]

Conrad --

You must open each of the other projects to see the task names. The other
way to handle this is to use the View Resource Assignments option in PWA.
Hope this helps.
 