Summary Task display incorrect on custom text field

S

Scott Morrissey

We have a custom task text field similar to the "Status" field - but with a
slightly different formula for determining the task status (i.e. Late,
Future, On Schedule, etc.).

This works fine at the task level - but the summary tasks are not
calculating correctly. For instance, all tasks under a summary level are
completed, but the summary is showing Future. The %Complete column on the
Summary line itself shows 100%. Why is this not showing a status of Complete?
Is there an issue with calculated custom text fields on summary tasks?
 
D

Dale Howard [MVP]

Scott --

Open the Enterprise Global file and then click Tools - Customize -
Enterprise Fields. Select his particular text field and check the
"Calculation for task and group summary rows" option. Have you set this
option, and if so, how? Let us know.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top