We have a custom task text field similar to the "Status" field - but with a
slightly different formula for determining the task status (i.e. Late,
Future, On Schedule, etc.).
This works fine at the task level - but the summary tasks are not
calculating correctly. For instance, all tasks under a summary level are
completed, but the summary is showing Future. The %Complete column on the
Summary line itself shows 100%. Why is this not showing a status of Complete?
Is there an issue with calculated custom text fields on summary tasks?