Dear all,
as far as I know it is not possible to display the summary tasks
within update view for project managers.
We are facing the problem with multi-repeating process tasks (same
task names) and thus the project manager is loosing the overview of
updates for these tasks. I am quite sure that some of you are facing
the same problem.
Does anyone know some workarounds?
Is it possible to adjust the update page in another way? (e.g.
computed fields etc.?)
If so, what view do we have to adjust?
Regards,
Thomas
as far as I know it is not possible to display the summary tasks
within update view for project managers.
We are facing the problem with multi-repeating process tasks (same
task names) and thus the project manager is loosing the overview of
updates for these tasks. I am quite sure that some of you are facing
the same problem.
Does anyone know some workarounds?
Is it possible to adjust the update page in another way? (e.g.
computed fields etc.?)
If so, what view do we have to adjust?
Regards,
Thomas