Summary task hours

S

Steve V.

Suddenly all the summary tasks have extra hours in them
For example, a summary task has 144 hours WORK and 106 hours ACTUAL. The three tasks under this one hav
Task 1 8 hours WORK, 8 hours ACTUA
Task 2 9 hours WORK, 0.5 hours ACTUA
Task 3 46.5 hours WORK, and 46.5 hours ACTUAL

If you have any suggestions, please hurry... the summary task hours seem to be growing as I futz with it
=/sr
 
J

Jan De Messemaeker

Hi Steve,

Either there are moire tasks than that under the summary or the sumary
itself has resources attached to it

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Steve V. said:
Suddenly all the summary tasks have extra hours in them.
For example, a summary task has 144 hours WORK and 106 hours ACTUAL. The
three tasks under this one have
Task 1 8 hours WORK, 8 hours ACTUAL
Task 2 9 hours WORK, 0.5 hours ACTUAL
Task 3 46.5 hours WORK, and 46.5 hours ACTUAL.

If you have any suggestions, please hurry... the summary task hours seem
to be growing as I futz with it.
 
S

Steve V.

Thank you, messr.Messemaeker.
I envy your knowledge.
I discovered the resources on the summary tasks just before your message.

Now all that remains is a troublesome recurring task.
1 hour every Friday for 15 weeks, one resource.
The recurring task received a WORK summary calculation of 576 hours, and REMAINING of 576 hours, with a percent complete of zero. Any suggestions?

Steve VanArsdale
 
J

John Beamish

If there are 0 hours of Actual Work entered against it then you could simply
display all of the detail tasks and set the Work to an appropriate amount
for each detail task.

If Actual Work has been entered then you should probably set Work so that it
matches Actual Work.

This should set Remaining Work to the correct value.

Steve V. said:
Thank you, messr.Messemaeker.
I envy your knowledge.
I discovered the resources on the summary tasks just before your message.

Now all that remains is a troublesome recurring task.
1 hour every Friday for 15 weeks, one resource.
The recurring task received a WORK summary calculation of 576 hours, and
REMAINING of 576 hours, with a percent complete of zero. Any suggestions?
 
J

Jan De Messemaeker

Hi Steve,

Cut the resource(s) from the recurring task
Now show the detail tasks
Select the lot (but not the recurring task itself)
Open the resource assignment window
assign the bncessatry resources to the detail tasks.
HTH


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Steve V. said:
Thank you, messr.Messemaeker.
I envy your knowledge.
I discovered the resources on the summary tasks just before your message.

Now all that remains is a troublesome recurring task.
1 hour every Friday for 15 weeks, one resource.
The recurring task received a WORK summary calculation of 576 hours, and
REMAINING of 576 hours, with a percent complete of zero. Any suggestions?
 