Steve Scott
We have a template with Summary tasks linked. It has been causing issues
with circular references but I am looking for a way of demonstrating how a
plan with linked summary tasks can cause this behaviour. Can anyone give me
an example of how I can set a simple plan up with summary tasks linked and
how I can then delete some tasks which then causes the circular reference
with teh root cause having been the summary task linking.
with circular references but I am looking for a way of demonstrating how a
plan with linked summary tasks can cause this behaviour. Can anyone give me
an example of how I can set a simple plan up with summary tasks linked and
how I can then delete some tasks which then causes the circular reference
with teh root cause having been the summary task linking.