A
abruncke
I have a summary task with 2 subtasks. Both of the subtasks are
reported complete - 100% done. The summary task shows 0% complete,
shouldn't it be 100% as all the subtasks are complete? This used to
work for me, but I had to reset my Windows profile and set options and
such back up. Something in that process seemed to break something.
Also, I have new tasks set to be on the date created and with fixed
units, but for some reason when I create a new task, it correctly sets
the constraint as start no earlier than today, but the actual start
date is the project start date, and project immediately tells me
(indicator in the 1st column) that this task is set to start before the
constraint date. They are directly conflicting
So many strange things going on that used to not happen - is there just
some corruption in my file? Should I just reinstall project?
reported complete - 100% done. The summary task shows 0% complete,
shouldn't it be 100% as all the subtasks are complete? This used to
work for me, but I had to reset my Windows profile and set options and
such back up. Something in that process seemed to break something.
Also, I have new tasks set to be on the date created and with fixed
units, but for some reason when I create a new task, it correctly sets
the constraint as start no earlier than today, but the actual start
date is the project start date, and project immediately tells me
(indicator in the 1st column) that this task is set to start before the
constraint date. They are directly conflicting
So many strange things going on that used to not happen - is there just
some corruption in my file? Should I just reinstall project?