Summary Task not showing 100% in complete column

P

Patrick Gage

Good Day:

I have a templated project plan that I am using and I am having trouble with one of my Summary Tasks not showing 100% complete when all the sub-tasks are at 100%. I am not able to even change the % complete by selecting it.

Any help would greatly be appreciated.

Pat
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top