Summary Task Question

B

Brian

Is there anyway for summary tasks to be displayed on the "Approve Timesheets"
or the "View task changes submitted by resources" page (preferably both)? We
have just upgraded to SP2a and we cannot see summary tasks on these pages.
In the Microsoft documentation, KB Article 890069 reports the following issue
that SP2a should take care of:

"The resource manager or the project manager cannot distinguish between tasks"

How does SP2a resolve this issue if it does not display the summary tasks?

Thanks!
 
D

Dale Howard [MVP]

Brian --

Good question. I am using Project Server Sp2a, but there is still no way to
display summary tasks on either the Approve Timesheets page or the Updates
page. I have no idea what the reference means in the KB article, therefore.
Sorry about the bad news.
 
B

Brian

Dale,

Thanks for the help. Now I know it's not just me! I hope that viewing
Summary Tasks on these pages will be possible in the 2007 version.

Thanks again,
Brian
 