Summary Task Slack Discrepancy

C

Chris

Hi

Can anyone tell me why my slack time for my summary task
is showing as 1 day when the slack time for the two tasks
that make up the summary task both have a slack time of 0
days?

I thought that it would naturally sum up the slack time
from the two "child" tasks?

Can anyone help - this is really frustrating me

Thanks in advance
Chris
 
M

MAM

Hi there

Do your child tasks start and end on the same day and are there any links between them

task Slack start date Finish date
Sum task 1 May 10 May 1
Child 1 0 May 10 May 14
Child 2 0 May 11 May 14 (if one of the child tasks start a day later or earlier from the other there will be a day slack in the summary task)

Hope this helps, if not could you cut and past the task info
 
C

Chris

Hi Mam

That is exactely whats happening, it's good to know that it's supposed to do
that, what I can't figure out is why. The second task is dependent on the
first and neither of them have any slack so why does the summary task show
it as having a days slack?

If you could shine a little light on it for me it would help greatly

Cheers, Chris

MAM said:
Hi there!

Do your child tasks start and end on the same day and are there any links between them:

task Slack start date Finish date
Sum task 1 May 10 May 14
Child 1 0 May 10 May 14
Child 2 0 May 11 May 14 (if one of the child
tasks start a day later or earlier from the other there will be a day slack
in the summary task)
 

Ask a Question