A
arno_
Ha,
I'm experiencing a strange phenomenon.
Here you see a sniped from one of the projects here, I only altered the
tasknames:
work actual work actual work protected
sumtask 10 uur 5 uur 10 uur
task1 10 uur 5 uur 5 uur
task2 0 uur 0 uur 0 uur
task3 0 uur 0 uur 0 uur
There isnt a resource on the summary task. It is in a Project Server
environment with Managed Timeperiode on, so actual work protected
represents the hours the resource on task1 entered through timesheet
(checked it). Synchronizing doesnt do anything (shouldnt because actual
work and actual work protected are equal). Being in a Managed
timeperiode it means it isnt possible that there has been a resource on
the summary task which wrote hours against it (it wouldnt be possible
to delete them)
Anyone an idea how this happens and better how to solve it?
Regards,
Arno
I'm experiencing a strange phenomenon.
Here you see a sniped from one of the projects here, I only altered the
tasknames:
work actual work actual work protected
sumtask 10 uur 5 uur 10 uur
task1 10 uur 5 uur 5 uur
task2 0 uur 0 uur 0 uur
task3 0 uur 0 uur 0 uur
There isnt a resource on the summary task. It is in a Project Server
environment with Managed Timeperiode on, so actual work protected
represents the hours the resource on task1 entered through timesheet
(checked it). Synchronizing doesnt do anything (shouldnt because actual
work and actual work protected are equal). Being in a Managed
timeperiode it means it isnt possible that there has been a resource on
the summary task which wrote hours against it (it wouldnt be possible
to delete them)
Anyone an idea how this happens and better how to solve it?
Regards,
Arno