Summary Tasks @ 0%

D

DogmanK

I have cut a summary task that has sub tasks from another MS Project file
into the file I am working on. I use paste special to make sure it pasted all
project info. All subtasks came over with their completion data but the
summary tasks are not calculating. I have checked \Tools\Options\Calulations
and they are set on Automatic. Any ideas????
 
J

Jan De Messemaeker

Hi,

Could be you have a circular relation.
Eliminate Paste Speciial links if any.
Eliminate links to and from summary tasks.
That should do it.
Hope this helps,
 
J

John

DogmanK said:
I have cut a summary task that has sub tasks from another MS Project file
into the file I am working on. I use paste special to make sure it pasted all
project info. All subtasks came over with their completion data but the
summary tasks are not calculating. I have checked \Tools\Options\Calulations
and they are set on Automatic. Any ideas????

DogmanK,
Do I have any ideas, yes. You're in trouble or headed there very
quickly. First of all, using paste special generates a paste link that
is prone to corruption and totally unnecessary. If you want to transfer
the data from one file to another on a one time basis, use a simple copy
and paste.

John
Project MVP
 
D

DogmanK

Thanks for the help, but it did not work. How can I find out if I have a
circular relationship. I elimnated all links from my summary task and just
cut and pasted as regular. Summary tasks are still showing 0%
 
J

Jan De Messemaeker

Hi,

Do children tasks have a nonzero duration or are they all milestones?
 
D

DogmanK

They have a non zero duration. I found and corrected a circular relationship
last night and it all works now. Thanks for your help
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top