D
David Schmitt
I have been unsuccessful in creating a Project view in Project Server that is
similar to the "Priority Keeping Outline Structure" grouping in Project
Professional. My goal is to group by one of the fields in the Project view,
but I want to keep the Outline Structure (the organization of the tasks
within the various summary tasks).
In Project Pro this is done by grouping first by Outline Number, then by the
field you want to group by. An example is the "Priority Keeping Outline
Structure" grouping that comes with Project Pro. However, if I group by
Outline Number in a Project Server view, there are two differences that make
the solution unusable:
1) The entire outline number of a task is used for grouping, rather than the
outline number of the summary tasks. Since each task has a unique outline
number, each task is in its own group. This renders the secondary grouping
useless.
2) The name of the task is not shown in the grouping so even if the first
problem didn't exist, I wouldn't know which grouping to expand.
For example, my Project Pro grouping is "2 Software | 2.1 Iteration 1 |
Resource1, Resource2, Resource3", my Project Server grouping is "2 | 2.1 |
2.1.1, 2.1.2, 2.1.3...".
Does anyone know a way I can replicate the functionality of the "Priority
Keeping Outline View" within Project Server? I want to use this view as a
means whereby everybody can view team's progress within an iteration.
Thanks for your help,
David Schmitt
Medical Simulation Corporation
similar to the "Priority Keeping Outline Structure" grouping in Project
Professional. My goal is to group by one of the fields in the Project view,
but I want to keep the Outline Structure (the organization of the tasks
within the various summary tasks).
In Project Pro this is done by grouping first by Outline Number, then by the
field you want to group by. An example is the "Priority Keeping Outline
Structure" grouping that comes with Project Pro. However, if I group by
Outline Number in a Project Server view, there are two differences that make
the solution unusable:
1) The entire outline number of a task is used for grouping, rather than the
outline number of the summary tasks. Since each task has a unique outline
number, each task is in its own group. This renders the secondary grouping
useless.
2) The name of the task is not shown in the grouping so even if the first
problem didn't exist, I wouldn't know which grouping to expand.
For example, my Project Pro grouping is "2 Software | 2.1 Iteration 1 |
Resource1, Resource2, Resource3", my Project Server grouping is "2 | 2.1 |
2.1.1, 2.1.2, 2.1.3...".
Does anyone know a way I can replicate the functionality of the "Priority
Keeping Outline View" within Project Server? I want to use this view as a
means whereby everybody can view team's progress within an iteration.
Thanks for your help,
David Schmitt
Medical Simulation Corporation