M
marchand.tim
Hello,
I am a new user of Microsoft Project 2003 Professional. I am trying to
outlining a multi phase process where the five phases are displayed as
summary tasks with each having a number of subsequent subtasks. When
entering duration for each subtask, the duration value calculated for
the summary task is the highest subtask duration. For example:
Duration
Summary Task 2
subtask 2
subtask 2
subtask 2
I would be interested in displaying a total duration for the summary
task (Phase) based on the time required to complete each subtask. So,
using the above example, the Summary Task duration value would be 6.
Can this be done?
Thank you very much for your time.
Cheers,
Tim
I am a new user of Microsoft Project 2003 Professional. I am trying to
outlining a multi phase process where the five phases are displayed as
summary tasks with each having a number of subsequent subtasks. When
entering duration for each subtask, the duration value calculated for
the summary task is the highest subtask duration. For example:
Duration
Summary Task 2
subtask 2
subtask 2
subtask 2
I would be interested in displaying a total duration for the summary
task (Phase) based on the time required to complete each subtask. So,
using the above example, the Summary Task duration value would be 6.
Can this be done?
Thank you very much for your time.
Cheers,
Tim