Summary Tasks' Duration not represented

J

John

Hi,

When I use summary tasks in 2002, the duration of the
summary tasks do not reflect in the task that is one level
higher in the hierarchy.

Eg. I have a task named "High" with the subtasks of "Low
1" with duration of 1 day and "Low 2" with duration of 2
days beneath it (indented). If I change the duration of
Low 2 to 8 days, the High task does not increase to
reflect the increased days.

Cheers,

John.
 
J

Jan De Messemaeker

Hi,

Summary tasks duration is the difference between the start of the first task
and the finish of the latest, not the sum of the durations of the outline
choildren.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top