P
PRibeiro
Dear All:
I am facing a puzzling problem when preparing a project.
I have summary tasks to add up the duration of segments of the project.
All sub-tasks have complete work days. The schedule is Monday-Sunday
(9:00-18:00) without rest days or holidays. The fact is that the summary
task comes with partial days in the duration (ex. 26.56 days), which is
really puzzling me as I cannot find any reasonable explanation for this
to happen.
Thanks in advance for your help.
I am facing a puzzling problem when preparing a project.
I have summary tasks to add up the duration of segments of the project.
All sub-tasks have complete work days. The schedule is Monday-Sunday
(9:00-18:00) without rest days or holidays. The fact is that the summary
task comes with partial days in the duration (ex. 26.56 days), which is
really puzzling me as I cannot find any reasonable explanation for this
to happen.
Thanks in advance for your help.