G
gb
In one .mpp, I have a two tasks. Then, in another .mpp I created
cross-project links as predecessors to the second task. In the first .mpp, I
indented these links to identify the first task as a summary task, and to
roll-up the start and finish date of the summary task.
However, the scheduled work hours from the cross-project links do not
roll-up. Additionally, these links don't appear to be addressed by the
critical path. Is this a limitation of Project? Or, am I doing this
incorrectly?
Any insight is greatly appreciated.
cross-project links as predecessors to the second task. In the first .mpp, I
indented these links to identify the first task as a summary task, and to
roll-up the start and finish date of the summary task.
However, the scheduled work hours from the cross-project links do not
roll-up. Additionally, these links don't appear to be addressed by the
critical path. Is this a limitation of Project? Or, am I doing this
incorrectly?
Any insight is greatly appreciated.