Summary tasks in Calendar view

S

Steve Schaedler

How do I display summary tasks in a Calendar view? I can
display the project summary task and I can display
milestones and I can display all tasks but I can't seem to
get only summary tasks displayed in a Calendar view.
 
M

Mike Glen

Hi Steve,

Welcome to the Microsoft Project newsgroup :)

Format/Bar Styles/select Summary and on the right, select Bar type, Pattern
and Colour. You might have to widen the space for each week for them to
show up by clicking and dragging down the dividing line between weeks.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 