summary tasks in the Update view

I

Itzik

Hi,
If for example I have a work plan like this one:
Summary task1
Detail task 1.1
Detail task 1.2
And Resource A is assigned to Detail task 1.2.
In his timesheet view he can choose to see summary tasks as well, and then
he will see:
Summary task1
Detail task 1.2
He will report his hours on Detail task 1.2 and update the project manager.
The project manager will then go to the "update" view and will see this:
Resource A
Task Update
Detail task 1.2
But he will not see the summary task.
How can it be resolved (it's very helpful to see the summary task in order
to understand where are we in the work plan, in many cases we have many
detail tasks with the same name for different summary tasks).
Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top